Three to five years, on the record so far: five years after the 2021 Lytton fire only 20 homes had been rebuilt and occupied, and 21 months after the 2023 McDougall Creek fire West Kelowna had received 44 applications to rebuild a home out of 191 destroyed.
Building a house takes eight to twelve months. The years are spent before anyone is allowed to start.5 Four things stand between a burned lot and a building permit, and they tend to run one after another even though most of them do not depend on each other.
Insurance settlement. Total-loss claims stall on replacement-cost disputes and on underinsurance, because construction costs rise faster than coverage gets updated. Temporary accommodation is covered only for a limited period.
Debris removal. Nothing starts until the lot is clear, and after a major fire that happens on a program schedule rather than yours.
Archaeology. The part specific to BC. Under the Heritage Conservation Act ground cannot be disturbed on a protected site without an assessment and a permit, the homeowner pays, and in Lytton two archaeologists were delegated to the whole village.4 Quotes to Lytton homeowners ran $26,000 to $46,000, with one at $82,000.
Permitting and design. Several more months at the end, once everything else has cleared.
The record from the last three fires
Lytton burned on June 30, 2021. Five years later, 20 homes were rebuilt and occupied.1 The pace has picked up, but the first four years produced almost nothing.
The McDougall Creek fire took 191 homes around West Kelowna in August 2023. By May 2025 the city had received 102 permit applications, of which 51 were for demolition and 44 were to rebuild a home.2 The same fire destroyed 13 structures on Westbank First Nation land, and by the same date nearly every one of those homes was rebuilt or under construction, because the Nation controlled its own permitting and went straight from demolition to approval.2
Jasper, across the border in Alberta and inside a national park, burned in July 2024. Parks Canada's dashboard on August 10, 2026 showed 54 of 374 properties at occupancy, 96 under construction, and 187 still in design or application.3 Two years on, half the properties had not reached a building permit application.
If you are facing this
Start the archaeology assessment while your insurance claim is still open. It is the longest item, it does not depend on the settlement, and your policy will not reimburse it. Assume the four stages can overlap, because nobody else will overlap them for you. And ask early who controls your permitting, because in the one case where the same fire hit both sides of a jurisdictional line, that mattered more than anything else.